Projek Pembinaan Kuarters, Stesen Dan Pejabat Jabatan Meterologi di bawah RMK9, MMD

Name
Projek Pembinaan Kuarters, Stesen Dan Pejabat Jabatan Meterologi di bawah RMK9, MMD
Owner
Jabatan Meteorologi (MetMalaysia)
Sector
Construction
Type
Facilities
Facilities
Expected Completion 2010
Geographical Scale
National Project
Initial Cost
RM62.35 million (RMKe-9)
Year Started
2007 Year End 2011
Duration
32-52 weeks
Extension
43 -225 days
Profile
Under the Ninth Malaysia Plan, the Malaysian Meteorological Department planned to build quarters, stations and offices as well as procure equipment in improving its services/facilities offered to customers and officers. MOSTI decided that all physical projects should be done conventionally and the Jabatan Kerja Raya (JKR) was appointed as the implementing agency. All projects were handed over to PWD and the tender process was done at PWD Headquarters and State PWD while State/District PWD acted as Superintending Officer/Representative of Superintending Officer. Statistics: The budgeted ceiling was RM156 million for 47 projects inclusive of 30 (63.8%) physical projects involving 12 locations in the entire country with total allocation costs of RM62.35 million and the remaining amount for procurement of equipment.